Kitchen floor layers lifted from a 1940s stucco cottage before the room is reworked
Example project
- Home
- 1940s stucco cottage in Inglewood with a kitchen floor of linoleum over older tile
- Original request
- Move the sink wall and the range, then lay one new floor through the kitchen
- Testing
- A Cal/OSHA-certified asbestos consultant samples the linoleum, the tile under it and the glue at the doorway
- Found
- Asbestos in the 9-inch tile and its glue
- Clear
- The linoleum
- Area
- About 250 sq ft of kitchen floor
- Timeline
- Notice no later than 10 working days ahead, then two working days
- Cost
- $3,400
Scope of work
A lab result for each layer, the district notice, the kitchen sealed with air filters running, the linoleum lifted and the tile and glue taken up wet, bagged disposal and a cleanup. The clearance air test and the new floor are separate.
Project overview
In this example, the owner of a 1940s stucco cottage is reworking the kitchen, with the sink wall and the range moving to new spots. The plumber will cut into the floor, so the floor layers get sampled first.
The tile and glue under the linoleum test positive. The abatement crew removes them before the plumber and the flooring installer start.
The goal
The goal is a bare kitchen subfloor, so the plumber and the installer work with nothing positive left beneath them.
Process
- First visit A Cal/OSHA-certified asbestos consultant samples the linoleum, the tile and the glue.
- Before work The abatement contractor files the district notice online.
- Day one The kitchen is sealed, the linoleum comes up and the tile is lifted by hand.
- Day two The glue is removed wet, the floor is cleaned and an independent consultant tests the air.
Planning right
- Empty the lower cabinets the day before.
- Plan meals away from the kitchen on both work days.
- Book the plumber for a day after the air results.
- Keep a copy of the report.