Example Asbestos Removal Projects in Inglewood

Seven example jobs are set out below for Inglewood, Culver City and West Hollywood, from a cottage kitchen to a six-unit building. Each lists the samples, the removal, the work days and an estimated cost.

Kitchen floor layers lifted from a 1940s stucco cottage before the room is reworked

Example project

Home
1940s stucco cottage in Inglewood with a kitchen floor of linoleum over older tile
Original request
Move the sink wall and the range, then lay one new floor through the kitchen
Testing
A Cal/OSHA-certified asbestos consultant samples the linoleum, the tile under it and the glue at the doorway
Found
Asbestos in the 9-inch tile and its glue
Clear
The linoleum
Area
About 250 sq ft of kitchen floor
Timeline
Notice no later than 10 working days ahead, then two working days
Cost
$3,400

Scope of work

A lab result for each layer, the district notice, the kitchen sealed with air filters running, the linoleum lifted and the tile and glue taken up wet, bagged disposal and a cleanup. The clearance air test and the new floor are separate.

Project overview

In this example, the owner of a 1940s stucco cottage is reworking the kitchen, with the sink wall and the range moving to new spots. The plumber will cut into the floor, so the floor layers get sampled first.

The tile and glue under the linoleum test positive. The abatement crew removes them before the plumber and the flooring installer start.

The goal

The goal is a bare kitchen subfloor, so the plumber and the installer work with nothing positive left beneath them.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the linoleum, the tile and the glue.
  2. Before work The abatement contractor files the district notice online.
  3. Day one The kitchen is sealed, the linoleum comes up and the tile is lifted by hand.
  4. Day two The glue is removed wet, the floor is cleaned and an independent consultant tests the air.

Planning right

  • Empty the lower cabinets the day before.
  • Plan meals away from the kitchen on both work days.
  • Book the plumber for a day after the air results.
  • Keep a copy of the report.

Get a free quoteMore about floor tile and mastic removal

Wrapped attic ducts removed before a heat pump goes in

Example project

Home
1950s house in Culver City with a furnace in the hall closet and ducts through the attic
Original request
Swap the furnace and the cooling coil for a heat pump with all-new ducts
Testing
A Cal/OSHA-certified asbestos consultant samples the wrap on the main trunk, a branch and the tape at the registers
Found
Asbestos in the wrap on the trunk and its branches
Clear
The register tape
Area
About 180 ft of duct in the attic
Timeline
Notice no later than 10 working days ahead, then two working days
Cost
$4,300

Scope of work

The attic hatch and the closet sealed, wet removal of the wrapped ducts into labeled bags, bagged disposal and a cleanup. The survey, the clearance air test, the heat pump and the new ducts are separate.

Project overview

In this example, the owners of a 1950s house in Culver City are installing a heat pump. Taking out the old ducts counts as renovation under the district’s rule, so the wrap is sampled before the installer goes up.

The wrap on the trunk and its branches tests positive. The abatement crew removes the old runs first, and the installer brings the new ducts into a cleaned attic.

The goal

The goal is an attic with the old wrapped ducts gone, so the new system goes in clean.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the wrap and the register tape.
  2. Before work The abatement contractor files the district notice online, and the installer holds its date.
  3. Days one and two The hatch is sealed and the ducts are wetted, cut apart and bagged.
  4. Last An independent consultant tests the air, then the heat pump goes in.

Planning right

  • Clear the hall closet and the area under the hatch.
  • Ask the installer to start after the air results.
  • Plan for the old system to be off while the work is done.
  • Give the installer a copy of the report.

Get a free quoteMore about HVAC duct and pipe insulation removal

Bathroom and entry floors removed in a 1960s condominium before a remodel

Example project

Home
1960s condominium in West Hollywood, second floor, with two bathrooms and a vinyl entry and kitchen
Original request
Remodel both bathrooms and lay new floors from the front door to the kitchen
Testing
A Cal/OSHA-certified asbestos consultant samples the bathroom tile, the vinyl, the glue under each and the ceilings
Found
Asbestos in the sheet vinyl backing and glue in the entry and kitchen, and in the bathroom floor tile
Clear
The ceilings
Area
About 300 sq ft of floor
Timeline
Notice no later than 10 working days ahead, then three working days
Cost
$5,200

Scope of work

The unit sealed with air filters running, the vinyl and tile removed, the glue taken up wet, disposal records and a cleanup. The survey, the district notification fee, the clearance air test and the new floors are separate.

Project overview

In this example, a couple with a condo in West Hollywood plans to remodel both bathrooms and relay the floors in one run. A condominium is not a single-unit dwelling, so the survey applies to the job, and so does the district notice unless the removal stays under 100 square feet.

The bathroom tile and the entry vinyl test positive. The abatement crew removes them in one visit, and the remodel crew starts on bare slab.

The goal

The goal is a bare slab in every room being redone, so the remodel starts on clean concrete.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples every floor in the unit and both ceilings.
  2. Before work The abatement contractor files the district notice online, and the owners tell the board the work dates.
  3. Days one to three The unit is sealed and the floors come out, bathrooms first.
  4. Last An independent consultant tests the air, then the remodel starts.

Planning right

  • Ask the board about the freight elevator before work begins.
  • Pack the bathroom cabinets before the first work day.
  • Plan a place to stay for the work days.
  • Order tile and fixtures after the air results.

Get a free quoteMore about apartments, condos and commercial suites

Textured ceilings removed in two units and a landing after a roof leak

Example project

Building
1960s two-story building in Inglewood with six units and an open stairwell
Original request
Repair the water-stained ceilings in two top-floor units and the upper landing
Testing
A Cal/OSHA-certified asbestos consultant samples the ceiling texture in each unit and on the landing
Found
Asbestos in the ceiling texture in both units and on the landing
Area
About 700 sq ft of ceiling
Timeline
Notice no later than 10 working days ahead, then four working days
Cost
$6,300

Scope of work

Samples and lab results, the district notice, each unit and the landing sealed in turn with air filters running, the texture wetted and scraped into bags, a HEPA clean and the haul. The clearance air test, the roof repair, the drywall patching and the paint are separate.

Project overview

In this example, a landlord is fixing the ceilings in two top-floor units and the landing after a roof leak. The textured finish is old enough that the owner has it sampled before a drywall crew touches it.

The texture tests positive in all three spots. The abatement crew removes it from the damaged ceilings, one unit at a time, so the tenants move back in after each unit passes its air test.

The goal

The goal is dry, bare ceilings in both units, so the drywall crew repairs them without touching the old texture.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples each unit’s ceiling and the landing.
  2. Before work The abatement contractor files the district notice online, and the landlord gives the tenants the work dates.
  3. Days one to four Each unit is sealed and scraped in turn, and the landing is done last.
  4. Last An independent consultant tests the air in each unit before the drywall crew starts.

Planning right

  • Offer the tenants a clear schedule for each unit.
  • Move furniture to the middle of the room or out of it the day before.
  • Repair the roof before the new ceilings are finished.
  • Keep a copy of the report in the building file.

Get a free quoteMore about popcorn ceiling removal

Stucco and plaster removed from a detached garage before it is torn down

Example project

Home
1940s house in Inglewood with a detached one-car garage at the back of the lot
Original request
Take the garage down to make room for a larger backyard unit
Testing
A Cal/OSHA-certified asbestos consultant samples the exterior stucco coat, the inside plaster and the roofing felt
Found
Asbestos in the exterior stucco coat and the inside plaster
Clear
The roofing felt
Area
About 480 sq ft of wall surface, outside and inside
Timeline
Notice no later than 10 working days ahead, then two working days before the wrecking crew
Cost
$4,400

Scope of work

Samples and lab results, the district notice, plastic around the garage, wet removal of the positive coats into labeled bags, bagged disposal and a cleanup. The demolition, the clearance air test and the new unit are separate.

Project overview

In this example, an owner is tearing down a detached garage behind a 1940s house. Every demolition needs the district notice, however small the building, so the garage is sampled first.

The stucco coat and the plaster test positive and the roofing felt is clear. The abatement crew takes the two coats off, and the wrecking crew comes after.

The goal

The goal is a garage with the positive coats gone, so it comes down without releasing them.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the garage inside and out.
  2. Before work The abatement contractor files the district notice online.
  3. Days one and two Plastic goes up, and the stucco and plaster come off wet.
  4. Last An independent consultant checks the air, and the wrecking crew starts.

Planning right

  • Empty the garage the weekend before.
  • Mark the property line for the crews.
  • Keep a copy of the report.
  • Ask the wrecking crew to start after the air results.

Get a free quoteMore about renovation and demolition abatement

Ground-floor laundry room tile tested before the floor is replaced

Example project

Building
1960s apartment building in Inglewood with a shared ground-floor laundry room
Original request
Replace the worn floor tile in the laundry room
Testing
A Cal/OSHA-certified asbestos consultant takes samples of the floor tile, the glue and the wall texture
Found
Asbestos in the floor tile and its glue
Clear
The wall texture
Timeline
Lab results first, then the removal is booked
Estimated testing cost
$650

Scope of work

A visit by the consultant, a few samples, a lab result for each and a short report with the sample spots marked. Removing the tile is priced on its own.

Project overview

In this example, the manager of an apartment building wants a new floor in the shared laundry room. The old tile is cracked in front of the machines.

The tile and its glue test positive and the wall texture is clear. An apartment building is never a single-unit dwelling, so removal gets the survey, the district notice follows unless the work stays under 100 square feet, and the abatement crew is booked next.

The goal

The goal is a written report, so the new floor is planned around what is actually in the old one.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the tile, the glue and the wall.
  2. Results The report marks two positive materials and the clear wall.
  3. Next The abatement contractor files the district notice online and schedules the removal.
  4. Then The new floor is ordered for a date after the air test.

Planning right

  • Post the laundry room closing dates for residents.
  • Hold the flooring order until the report is in.
  • Do not take samples yourself, the consultant knows what to cut.
  • File the report with the building records.

Get a free quoteMore about asbestos testing and surveys

Wall compound removed behind a window that leaked

Example project

Home
1940s single-unit house in Inglewood with a bedroom window that leaked into the wall below it
Original request
Open the wall under the window for a moisture repair and close it with new wallboard
Testing
A Cal/OSHA-certified asbestos consultant samples the wallboard, the joint compound and the plaster layer
Found
Asbestos in the joint compound
Clear
The wallboard and the plaster layer
Area
About 70 sq ft of wall
Timeline
Less than 100 square feet of renovation, so no district notice, then one working day
Cost
$1,800

Scope of work

Plastic over the bedroom and a filter running, the positive compound taken off wet, bagged disposal and a cleanup. The survey, the moisture repair, the new wallboard and the paint are separate.

Project overview

In this example, a window leak has soaked the wall below it in a bedroom of a 1940s house. The repair crew will cut the wall open, so the owner has it sampled before the saw comes out.

The rule skips the survey for a single-unit house, and the district notice for any building, when less than 100 square feet is removed, but the testing is how the owner knows the amount. The compound tests positive, so the abatement crew removes it before the repair crew starts.

The goal

The goal is a clean wall opening, so the moisture repair is done on bare studs.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the wall layers.
  2. Results The lab marks the joint compound positive and the rest clear.
  3. Work day The bedroom is sealed and the compound is removed wet.
  4. Then The repair crew opens the wall and fixes the window flashing.

Planning right

  • Move the bed and dresser out of the room.
  • Mark the wet area for the repair crew.
  • Keep the lab report with the repair estimate.
  • Paint after the new wallboard has dried.

Get a free quoteMore about drywall, joint compound and plaster removal

Request a free asbestos removal quote

We recommend calling, but do feel free to contact us using this form. We'll get back to you with a free, personalized quote or additional questions as soon as possible. We're here to help.

Call (424) 414-6846

Call (424) 414-6846