Your contractor sends the notice through the district’s online application. Plan the building schedule so it reaches the district no later than 10 working days before any demolition or renovation starts.
Registration and licensing
Two checks on any contractor you hire for a big job. Ask for the C-22 Asbestos Abatement classification, or a qualifier with a passing asbestos certification exam result, and ask whether Cal/OSHA registration is on file for the employer. Both apply once the work reaches 100 square feet or more of asbestos-containing material, and a call to the Contractors State License Board will confirm the license number.
Air testing at the end
After removal, the air is tested by someone other than the crew, an independent consultant, because California bars removal contractors from clearance air monitoring.