The district’s rule lets wet removal, called Procedure 3, be used for nonfriable material only. Which method is allowed therefore depends partly on what the lab reports.
Small floors in a house
In any type of building, the notice and training provisions do not apply to a renovation where less than 100 square feet of asbestos-containing material is removed or stripped. Work practices and waste rules still apply, and demolition never qualifies. Any other floor job needs its notice no later than 10 working days before the work.
Disposal
Where the waste ends up depends on its condition. Under California’s hazardous waste table, asbestos is limited only when it is friable, powdered or finely divided, and the lab result shows whether the material is friable. Another agency may still limit disposal.